Project 26MI0069

DPWH infrastructure contract
Contract ID:
26MI0069
Fingerprint:
34fcbba6edacc6…4451c1d6f8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 18, 2026 (4 mos ago) · Target/actual end Aug 15, 2026
Description:
SAYRE ROAD-SITIO TAWAGON-KILAMBAY, BRGY. KIBUDTUNGAN CONNECTING TO SALAMA, BANISILAN ROAD IN SUPPORT OF THE COCONUT PROCESSING INDUSTRY (TREE LIFE ORGANIC COCO SUGAR) - STA. 11 + 523.87 - STA. 11 + 751.37, CARMEN, COTABATO
Category:
GAA 2026 CP
Implementing office:
DPWH Cotabato 3rd DEO · Region XII
Contractor:
PADER CONSTRUCTION & SUPPLY · DPWH contractor code 20213
Contract amount:
₱9,240,097.18 (₱9.2M)
Funding source:
Regular Infra - GAA 2026 CP
Budget year:
2026

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26MI0071Jun 18, 2026ASPHALT OVERLAY ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1646 + 239 - K1646 + 850Completed₱43.0M
26MI0001Jun 17, 2026(RE-BID) ASPHALT OVERLAY ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1649 + 670 - K1649 + 1000Completed₱19.8M
25MI0092Aug 19, 2025CONSTRUCTION OF ROAD, MALANDUAGE-DAGUPAN SECTION, KABACAN, COTABATOOn-Going₱46.5M
25MI0080Jul 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, USM-KABACAN IN KABACAN, COTABATOCompleted₱4.7M
25MI0087Jul 29, 2025CONSTRUCTION OF ROAD, PISAN, KABACAN, COTABATOCompleted₱46.5M
25M00006Jul 9, 2025CONSTRUCTION OF PULANGI RIVERBANK PROTECTION (DOWNSTREAM OF CARMEN BR., RIGHT BANK), PHASE II, STA. 0+000 - STA. 0+652.5, BARANGAY UGALINGAN, CARMEN, COTABATOOn-Going₱167.2M
25M00005Jul 7, 2025CONSTRUCTION OF KABACAN RIVER FLOOD CONTROL PROJECT (RUBBER TESTING CENTER), STA. 0+000 - STA. 0+648, BARANGAY POBLACION, KABACAN, COTABATOOn-Going₱157.7M
25MI0018May 23, 2025CONSTRUCTION OF KABACAN RIS, DRAINAGE RESHAPING AT MAYASONG - HINIGARAN, KABACAN, COTABATOCompleted₱9.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.