Project 26RE0046
DPWH infrastructure contract
Contract ID:
26RE0046
Fingerprint:
d2d2cd10f56392…3155c91a94 Verified
Status:
On-Going
Physical progress:
15.2%
Timeline:
Start Aug 3, 2026 (3 mos ago)
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS ALONG BACOLOD NORTH RD. K0111+851 - K0111+977
Category:
GAA 2026 OO-1
Implementing office:
DPWH Negros Occidental 5th DEO · Negros Island Region
Contractor:
GALFONS BUILDERS & SUPPLY, INC. · DPWH contractor code 46484
Contract amount:
₱22,048,750.23 (₱22.0M)
Funding source:
Regular Infra - GAA 2026 OO-1
Budget year:
2026
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26RE0047 | Aug 3, 2026 | ROAD WIDENING ALONG BACOLOD NORTH RD - K0124 + 238 - K0125 + 000 | On-Going | ₱31.7M |
| 26RE0044 | Jul 13, 2026 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, DA-AN LUNSOD BR. (B00179NR) ALONG BACOLOD NORTH RD | On-Going | ₱5.3M |
| 26RE0034 | Jun 29, 2026 | ROAD WIDENING ALONG BACOLOD NORTH RD - K0130 + 453 - K0130 + 919, K0132 + 233 K0132 + 904, K0153 + 056 - K0153 + 281, K0153 + 453 - K0153 + 483, K0156 + 501 - K0156 + 631 | On-Going | ₱36.1M |
| 26RE0038 | Jun 29, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY ALONG BACOLOD NORTH RD - K0118 + 531 - K0119 + 718 | On-Going | ₱55.7M |
| 25RE0034 | Jun 26, 2026 | ROAD WIDENING ALONG BACOLOD NORTH RD (S00425NR) K0117 + 739 K0118 + 290, K0118 + 398 K0118 + 531 | On-Going | ₱18.3M |
| 26RE0024 | Jun 15, 2026 | RECONSTRUCTION TO CONCRETE PAVEMENT ALONG BACOLOD NORTH RD - K0099+916 - K0100+125 | On-Going | ₱5.2M |
| 26RE0011 | May 20, 2026 | REHABILITATION/ MAJOR REPAIR OF ROAD SLOPE PROTECTION STRUCTURE ALONG BACOLOD NORTH RD. K0096+942 - K0097+042, K0102+796 - K0102+814 | On-Going | ₱4.8M |
| 25RE0019 | Sep 3, 2025 | CONSTRUCTION (COMPLETION) OF DPWH BUILDING OF NEGROS OCCIDENTAL SUB DEO, SAN CARLOS CITY, NEGROS OCCIDENTAL | On-Going | ₱29.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.