Project 17DN0013
DPWH infrastructure contract
Contract ID:
17DN0013
Fingerprint:
b4fe77335dd4fe…38edff7816 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2017 (9 yrs 8 mo ago) · Target/actual end Aug 18, 2017
Description:
MFO-1 NATIONAL ROAD NETWORK SERVICES-NETWORK DEVELOPMENT-OFF CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, SECONDARY ROAD, MANILA EAST ROAD, K0036+1007-K0037+340, BINANGONAN, RIZAL
Category:
Flood Control/Hydraulics/Drainage, Roads: Construction - PCCP
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
2H2L CONSTRUCTION · DPWH contractor code 16293
Contract amount:
₱9,071,499.26 (₱9.1M)
Funding source:
Regular Infra - Flood Control/Hydraulics/Drainage, Roads: Construction - PCCP
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0097 | Jun 26, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD - K0033+276 - K0033+551, RIZAL (FIRST DISTRICT) | On-Going | ₱7.1M |
| 25DN0098 | May 29, 2025 | CONSTRUCTION OF ROAD AT BARANGAY ITHAN TO BARANGAY KALINAWAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱19.0M |
| 25DN0101 | May 29, 2025 | CONSTRUCTION OF FLOOD STRUCTURE, CREEK, W. CERRERO GOING TO F. CEQUEÑA, BARANGAY MACAMOT, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱9.5M |
| 25DN0106 | May 29, 2025 | CONSTRUCTION OF BOX CULVERT CONNECTING BARANGAY JANOSA AND BARANGAY KAYTOME BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱4.9M |
| 25DN0112 | May 29, 2025 | FY 2025 CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱2.6M |
| 25DN0067 | May 27, 2025 | CONSTRUCTION OF ROAD AT CABLE WAY GOING TO KASINAY, BARANGAY MACAMOT AND BARANGAY DARANGAN, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱67.5M |
| 25DN0044 | May 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN JUAN CREEK, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱19.6M |
| 25DN0056 | May 26, 2025 | CONSTRUCTION OF BREAKWATER, BARANGAY KALINAWAN GOING TO BARANGAY PIPINDAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱9.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.