Completed
Physical progress:
100%
Timeline:
Start Sep 16, 2019 (7 yrs 1 mo ago) · Target/actual end Oct 30, 2019
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BOOL EAST, CULABA, BILIRAN (11.68198, 124.51802°)
Category:
Buildings and Facilities
Implementing office:
DPWH Biliran DEO · Region VIII
Contractor:
W.B. ALAGAO CONSTRUCTION · DPWH contractor code 15622
Contract amount:
₱982,500.00 (₱982.5K)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
64563a5fc1a3…Sep 3, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BILIRAN ED₱982,500.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26IA0005May 13, 2026NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1061+078 - K1062+400On-Going₱47.2M
25IA0145Jun 30, 2025CONSTRUCTION OF ROAD, BARANGAY BINONGTOAN, CULABA, BILIRANOn-Going₱14.8M
25IA0150Jun 30, 2025CONSTRUCTION OF SEAWALL, BARANGAY SAN ROQUE, CULABA, BILIRANCompleted₱14.7M
25I00128Apr 16, 2025ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD. - K1071+895 - K1072+180On-Going₱144.6M
25IA0128Mar 25, 2025CONCRETING OF BRGY. BOOL-WEST FMR, BRGY. BOOL-WEST, CULABA, BILIRANOn-Going₱14.9M
25IA0049Mar 10, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1066+170 - K1067+900On-Going₱36.2M
25IA0122Mar 7, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BACOLOD, CULABA, BILIRANCompleted₱4.9M
25IA0013Mar 4, 2025CONSTRUCTION OF BOOL FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE V, CULABA, BILIRANCompleted₱49.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.