Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20BE0057

DPWH infrastructure contract
Contract ID:
20BE0057
Fingerprint:
8105907b90e12f…83ad476b1a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 29, 2020 (5 yrs 11 mo ago) · Target/actual end Mar 30, 2021
Description:
ROAD CONCRETING OF STA. FILOMINA ROAD, STA. FILOMINA, STO. TOMAS, ISABELA
Category:
Roads
Implementing office:
Contractor:
DRAGON TWELVE BUILDERS AND CONSTRUCTION SUPPLY · DPWH contractor code 39808
As listed: DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
Contract amount:
₱18,619,855.50 (₱18.6M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ed1f28ff9371…Nov 13, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 1ST DEO₱18,619,855.50

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25BE0084Jul 14, 2025CONCRETING OF BUBUG FMR (PHASE I), BRGY. BUBUG, STO. TOMAS, ISABELAOn-Going₱14.5M
25BE0109Jul 14, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM AT BARANGAY BALELLENG, SANTO TOMAS, ISABELAOn-Going₱4.8M
25BE0128Jul 14, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF SLOPE PROTECTION AND CROSS DRAIN ALONG BAGABAG CREEK, STO. TOMAS, ISABECompleted₱14.4M
25BE0091Jun 19, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PHASE 5, BARANGAY MALAOn-Going₱38.4M
25BE0024Feb 26, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF CONCRETE ROAD AT BARANGAYCompleted₱14.7M
24BE0149Dec 11, 2024CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD ALONG BARANGAY BUBUGOn-Going₱96.5M
24BE0146Sep 5, 2024CONCRETING OF BRGY. BARUMBONG FMR, BRGY. BARUMBONG, STO. TOMAS, ISABELAOn-Going₱17.4M
24BE0091Jun 13, 2024CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR /STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BARANGAY BUBUG-SANTO TOMAS-QUEZON ROAD, SANTOOn-Going₱29.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.