Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20CC0221

DPWH infrastructure contract
Contract ID:
20CC0221
Fingerprint:
1a9a801ad400ae…58a1efe897 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 27, 2020 (5 yrs 11 mo ago) · Target/actual end May 25, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT, BRGY. POBLACION, PLARIDEL, BULACAN
Category:
Buildings and Facilities
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
GENUINE BUILDERS · DPWH contractor code 40911
Contract amount:
₱14,394,629.94 (₱14.4M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
c2835e29e6b2…Nov 11, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO₱14,394,629.94

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CC0545Jun 11, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY BULIHAN, PLARIDEL, BULACANOn-Going₱14.5M
25CC0465May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SIPAT, PLARIDEL, BULACANOn-Going₱14.5M
25CC0532May 23, 2025CONSTRUCTION OF MULTI- PURPOSE BUILDING BARANGAY SAN JOSE, PLARIDEL, BULACANOn-Going₱14.5M
25C00493Apr 14, 2025ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MAHARLIKA HIGHWAY, PROVINCE OF BULACANOn-Going₱114.0M
25CC0300Apr 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PUROK 3, BARANGAY BULIHAN, PLARIDEL, BULACANOn-Going₱92.6M
25CC0301Apr 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PUROK 1, BARANGAY BAGONG SILANG, PLARIDEL, BULACANOn-Going₱92.8M
25CC0081Feb 25, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER AT BARANGAY SANTA LUCIA (PUROK 5 TO PUROK 6), CALUMPIT, BULACANOn-Going₱82.0M
25CC0090Feb 25, 2025CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY BAGBAGUIN (PUROK 5), PANDI, BULACANOn-Going₱74.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.