Project 20FM0041
DPWH infrastructure contract
Contract ID:
20FM0041
Fingerprint:
bf7074d67141e4…c5d460bfa0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 27, 2020 (6 yrs 5 mo ago) · Target/actual end Oct 22, 2020
Description:
LOCAL PROGRAM - CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, BATUAN, MASBATE.
Category:
Water Provision and Storage
Implementing office:
DPWH Masbate 1st DEO · Region V
Contractor:
TRISAN CONSTRUCTION & DEVELOPMENT · DPWH contractor code 35083
As listed: TRISAN CONSTRUCTION AND DEVELOPMENT
Contract amount:
₱26,681,181.03 (₱26.7M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a3e4a24c5fe5… | Feb 26, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MASBATE 1ST DEO | ₱25,879,081.08 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FM0054 | Jul 14, 2025 | CONVERGENCE PROGRAM - CONSTRUCTION/ REHABILITATION OF RAINWATER COLLECTORS IN PUBLIC FACILITIES - CONSTRUCTION/ REHABILITATION OF RAINWATER COLLECTORS SYSTEM (RWCS) IN PUBLIC FACILITIES. | Completed | ₱2.5M |
| 25FM0055 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BATUAN CENTRAL SCHOOL, BATUAN, MASBATE. | On-Going | ₱14.4M |
| 25FM0051 | Apr 7, 2025 | CONCRETING OF BRGY. RIZAL FMR, BRGY. RIZAL, BATUAN,MASBATE. | Completed | ₱14.9M |
| 25FM0011 | Mar 27, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF SHORE PROTECTION STRUCTURE,BARANGAY DANAO, BATUAN, MASBATE. | Completed | ₱47.5M |
| 25FM0018 | Mar 27, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORE PROTECTION STRUCTURE, LAGUNDI, BARANGAY BURGOS, BATUAN, MASBATE. | On-Going | ₱47.5M |
| 25FM0042 | Mar 27, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY RIZAL, BATUAN, MASBATE | Completed | ₱26.0M |
| 25FM0007 | Feb 24, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRASTRUCTURE PROGRAM ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF ROAD, BARANGAY MABUHAY, BATUAN, MASBATE. | Completed | ₱12.5M |
| 24FM0042 | Apr 22, 2024 | CONCRETING OF BRGY. BURGOS TO BRGY. SAWANG FMR, BRGY. BURGOS, BATUAN, MASBATE. | Completed | ₱14.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.