Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20J00180

DPWH infrastructure contract
Contract ID:
20J00180
Fingerprint:
575e22fe2b2dd6…65ec748ca1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 23, 2020 (5 yrs 11 mo ago) · Target/actual end Nov 27, 2021
Description:
CONSTRUCTION OF SLOPE PROTECTION/CONCRETING ALONG CAMP ANDRES ROMANDIER NATIONAL ROAD, SULU
Category:
Roads
Implementing office:
DPWH Region IX · Region IX
Contract amount:
₱144,204,978.52 (₱144.2M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25J00185Sep 5, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TIPTIPON, PANGLIMA ESTINO, SULUOn-Going₱4.9M
24J00089May 3, 2024REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - ROMANDIER - CAMP ANDRES - TANDUH BATO ROADOn-Going₱96.4M
23J00114Apr 11, 2023PREVENTIVE MAINTENANCE - SECONDARY ROAD ROMANDIER - CAMP ANDRES - TANDUH BATO ROADCompleted₱10.4M
23J00116Apr 11, 2023ROAD WIDENING - SECONDARY ROADS - ROMANDIER - CAMP ANDRES - TANDUH BATO (SO0022SL)Completed₱171.6M
22J00101Feb 22, 2022PREVENTIVE MAINTENANCE - SECONDARY ROADS - SEIT -TAYUNGAN - CAMP ANDRES ROAD, SULU 2ND (BARMM)Completed₱144.6M
20J00200Nov 16, 2020CONSTRUCTION OF BUD SIBALO MULTI-PURPOSE CENTER, SITIO SIBALO, BRGY. PUNAY, PANGLIMA ESTINO, SULUCompleted₱24.6M
20J00100May 28, 2020ROAD WIDENING ALONG PUNAY ROAD, SULUCompleted₱86.0M
19J00134Jan 21, 2020CONCRETING OF BRGY. GATA - GATA FMR, BRGY. GATA - GATA, PANGLIMA ESTINO, SULUCompleted₱14.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.