Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20MA0112

DPWH infrastructure contract
Contract ID:
20MA0112
Fingerprint:
279b34a00e68af…2ff103556f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 24, 2020 (6 yrs 1 mo ago) · Target/actual end Feb 10, 2021
Description:
CONSTRUCTION/REHABILITATION OF PROVINCIAL TOURISM OFFICE/MULTI-PURPOSE BUILDING, OLD MAGUINDANAO CAPITOL SITE, SHARIFF AGUAK, MAGUINDANAO
Category:
Buildings and Facilities
Implementing office:
Contractor:
RNS CONSTRUCTION ENGINEERING · DPWH contractor code 34046
Contract amount:
₱8,890,702.05 (₱8.9M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
d27640e7be47…Sep 21, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII - COTAB₱8,890,702.05

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25M00161Jul 9, 2025PREVENTIVE MAINTENANCE - MAHARLIKA HIGHWAY (MARBEL-ALLAH VALLEY-COTABATO RD) - K1781+598-K1783+198, DATU ABDULLAH SANGKI, MAGUINDANAO DEL SURCompleted₱121.5M
23M00225Dec 11, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING (PROVINCIAL LIBRARY), PROVINCIAL CAPITOL, SHARIFF AGUAK, MAGUINDANAOCompleted₱18.8M
23M00123Sep 18, 2023CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), BARANGAY POBLACION, SHARIFF AGUAK, MAGUINDANAOCompleted₱14.8M
23M00201Jun 27, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY POBLACION, SHARIFF AGUAK, MAGUINDANAOOn-Going₱4.8M
23M00126Jun 23, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING CENTER) IN BARANGAY LIMPONGGO, DATU HOFFER AMPATUAN, MAGUINDANAOCompleted₱6.8M
23M00195Jun 23, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM) IN BARANGAY LIMPONGGO, DATU HOFFER AMPATUAN, MAGUINDANAOCompleted₱4.8M
21M00133Feb 24, 2022CONSTRUCTION OF MULTI-PURPOSE BUILDING (PROVINCIAL TOURISM OFFICE) AT THE OLD MAGUINDANAO CAPITOL SITE IN SHARIFF AGUAK, MAGUINDANAOCompleted₱7.7M
21M00097Feb 14, 2022ASPHALT OVERLAY (CARRIAGEWAY) ALONG COTABATO-ALA-MARBEL ROAD, STA. 0+000 STA. 1+315, SHARIFF AGUAK, MAGUINDANAOCompleted₱33.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.