Project 21DH0041
DPWH infrastructure contract
Contract ID:
21DH0041
Fingerprint:
82fa8530a21018…a4536d4759 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 22, 2021 (5 yrs 8 mo ago) · Target/actual end Aug 20, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BULDING (COVERED COURT), BRGY. SAN JOSE (MUNICIPAL TOWN PLAZA), PANGIL, LAGUNA
Category:
Buildings and Facilities
Implementing office:
DPWH Laguna 1st DEO · Region IV-A
Contractor:
11 DIAMOND EAGLE CONSTRUCTION CORPORATION (FORMERLY:11 DIAMOND EAGLE CONSTRUCTION) · DPWH contractor code 33328
Contract amount:
₱6,895,059.19 (₱6.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DH0039 | Aug 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANGIL LAKESHORE, PANGIL, LAGUNA | On-Going | ₱93.6M |
| 24DH0079 | Sep 5, 2024 | CONSTRUCTION OF ROAD WITH BOX CULVERT, SITIO SAUDI, BARANGAY BALIAN, PANGIL, LAGUNA | On-Going | ₱8.2M |
| 24DH0072 | Aug 23, 2024 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES BALIAN BR. (B03194LZ) ALONG PAETE-FAMY POB. RD., PANGIL, LAGUNA | Completed | ₱1.4M |
| 24DH0037 | Mar 22, 2024 | CONSTRUCTION (COMPLETION) OF MULTIPURPOSE BUILDING (COVERED COURT) AT BARANGAY ISLA, PANGIL, LAGUNA | Completed | ₱3.0M |
| 24DH0030 | Mar 1, 2024 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANGIL RIVER, PANGIL, LAGUNA | Completed | ₱96.5M |
| 24DH0020 | Feb 23, 2024 | CONSTRUCTION OF RIVER CONTROL ALONG PANGIL RIVER, PANGIL, LAGUNA | Completed | ₱77.9M |
| 23DH0074 | Jul 12, 2023 | CONSTRUCTION OF ROAD, BARANGAY NATIVIDAD, PANGIL, LAGUNA | Completed | ₱23.2M |
| 23DH0048 | Apr 1, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY SAN JOSE, PANGIL, LAGUNA | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.