Project 21LF0118
DPWH infrastructure contract
Contract ID:
21LF0118
Fingerprint:
5ce2575a8b34d7…8b51311d89 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 27, 2021 (5 yrs 6 mo ago) · Target/actual end Jul 25, 2021
Description:
CONSTRUCTION OF WATER SUPPLY SYSTEM OF BARANGAY SAN IGNACIO, MANAY, DAVAO ORIENTAL
Category:
Water Provision and Storage
Implementing office:
DPWH Davao Oriental 1st DEO · Region XI
Contractor:
JJR ACE CONSTRUCTION AND SUPPLY CORP. · DPWH contractor code 44145
Contract amount:
₱4,942,310.93 (₱4.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LF0130 | Jun 9, 2025 | CONSTRUCTION OF COASTAL PROTECTION, PROTECTING SURIGAO DEL SUR BDRY.- DAVAO ORIENTAL COASTAL RD. (PINAKPAKAN SECTION), MANAY, DAVAO ORIENTAL | On-Going | ₱142.6M |
| 25LF0143 | Jun 9, 2025 | CONSTRUCTION OF ROAD, FROM JUNCTION TO SITIO MIDSAYAP, BARANGAY OLD MACOPA MANAY, DAVAO ORIENTAL | On-Going | ₱95.0M |
| 25LF0148 | Jun 9, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS) ALONG SURIGAO DEL SUR BDRY-DAVAO OR COASTAL RD- K1657+000-K1658+703 MANAY, DAVAO ORIENTAL | Completed | ₱648.9K |
| 25LF0025 | Apr 8, 2025 | SAN IGNACIO BYPASS ROAD, DAVAO ORIENTAL | On-Going | ₱88.0M |
| 25LF0031 | Apr 8, 2025 | NHJ-LINGAYAO TO SITIO SUMANDING OF BRGY. SAN IGNACIO CONNECTING MANAY PUBLIC TERMINAL TO COCONUT PROCESSING, MANAY, DAVAO ORIENTAL | Completed | ₱6.9M |
| 25LF0077 | Apr 8, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM COVERED COURT) SITIO LIBUAC BARANGAY OLD MACOPA MANAY, DAVAO ORIENTAL | Completed | ₱7.9M |
| 25LF0083 | Apr 8, 2025 | CONSTRUCTION OF EVACUATION CENTER, BARANGAY MABINI MANAY, DAVAO ORIENTAL | Completed | ₱7.8M |
| 25LF0047 | Apr 7, 2025 | CONSTRUCTION OF ROAD, FROM POBLACION TO PUROK DANGO, BARANGAY MANREZA, MANAY, DAVAO ORIENTAL | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.