Project 22CE0057

DPWH infrastructure contract
Contract ID:
22CE0057
Fingerprint:
1391c9bff55dcb…0d35bf462c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2022 (4 yrs 8 mo ago) · Target/actual end Sep 15, 2022
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BRGY. GOMEZ, LLANERA, NUEVA ECIJA
Category:
Flood Control and Drainage
Implementing office:
Contract amount:
₱49,000,000.00 (₱49.0M)
Funding source:
Regular Infra - GAA 2022 OO-2
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CE0195Jun 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GEN. RICARTE, LLANERA, NUEVA ECIJACompleted₱5.9M
25CE0196Jun 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VICTORIA, LLANERA, NUEVA ECIJACompleted₱4.9M
25CE0256Mar 25, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, JCT PINAGPANAAN-RIZAL-PANTABANGAN RD - K0136 + 000 - K0137 + 000Completed₱14.7M
25CE0109Mar 20, 2025REHABILITATION OF ROAD, BARANGAY SANTA BARBARA TO BARANGAY VILLA VINIEGAS, LLANERA, NUEVA ECIJACompleted₱9.7M
25CE0140Feb 17, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BAGUMBAYAN, LLANERA, NUEVA ECIJACompleted₱3.9M
25CE0102Feb 14, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY VICTORIA, LLANERA, NUEVA ECIJACompleted₱4.7M
25CE0112Feb 14, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PLARIDEL, LLANERA, NUEVA ECIJACompleted₱4.0M
25CE0113Feb 11, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN FRANCISCO, LLANERA, NUEVA ECIJACompleted₱2.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.