Project 22IB0150

DPWH infrastructure contract
Contract ID:
22IB0150
Fingerprint:
74df0ad9c2e8df…640bb94eed Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 16, 2023 (3 yrs 9 mo ago) · Target/actual end Jul 5, 2023
Description:
CONSTRUCTION OF 1STY2CL, BUSAY PRIMARY SCHOOL, MERCEDES, EASTERN SAMAR
Category:
Buildings and Facilities
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
YFL BUILDERS · DPWH contractor code 41246
Contract amount:
₱6,499,999.92 (₱6.5M)
Funding source:
Outside Infra - GAA 2022 DepEd BEFF
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
9e4313397f49…Dec 28, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO₱6,360,504.05

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IB0129Aug 14, 2025CONCRETING OF BRGY. 02 POBLACION TO BRGY. SAN ROQUE TO BRGY. BANUYO FMR, BRGY. 02 POBLACION, SAN ROQUE AND BANUYO, MERCEDES, EASTERN SAMAROn-Going₱5.0M
24IB0094Jun 3, 2024CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN JOSE ELEMENTARY SCHOOL, BARANGAY SAN JOSE, MERCEDES, EASTERN SAMARCompleted₱5.0M
24IB0001Feb 13, 2024CONSTRUCTION OF ROAD, BARANGAY BUYAYAWON TO BARANGAY 4, MERCEDES, EASTERN SAMAROn-Going₱9.7M
23IB0095Aug 3, 2023CONCRETING OF BRGY. SUNG-AN TO BRGY. BUSAY TO POBLACION 1 FMR, MERCEDES, EASTERN SAMARCompleted₱19.9M
23IB0116Aug 3, 2023CONSTRUCTION OF SOLAR WATER SYSTEM, MERCEDES, EASTERN SAMARCompleted₱9.8M
23IB0057Mar 22, 2023CONSTRUCTION OF ROAD, BARANGAY CAMBANTE - BARANGAY BUSAY, MERCEDES, EASTERN SAMARCompleted₱9.9M
22IB0078Apr 7, 2022CONSTRUCTION OF BARANGAY ROAD AT BARANGAY SUNG-AN, BARANGAY CAGBUNGA AND BARANGAY BOBON, MERCEDES, EASTERN SAMARCompleted₱4.9M
21IB0005Oct 7, 2021CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUSAY ELEMENTARY SCHOOL, BARANGAY BUSAY, MERCEDES, EASTERN SAMARCompleted₱3.5M