Project 24IB0001
DPWH infrastructure contract
Contract ID:
24IB0001
Fingerprint:
ff3429f4b2905b…ab517c5f12 Verified
Status:
On-Going
Physical progress:
97.9%
Timeline:
Start Feb 13, 2024 (2 yrs 8 mo ago)
Description:
CONSTRUCTION OF ROAD, BARANGAY BUYAYAWON TO BARANGAY 4, MERCEDES, EASTERN SAMAR
Category:
Roads
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
DRAGON CONSTRUCTION · DPWH contractor code 48354
Contract amount:
₱9,733,499.91 (₱9.7M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3f32215791c1… | Jan 26, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO | ₱9,733,499.91 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IB0129 | Aug 14, 2025 | CONCRETING OF BRGY. 02 POBLACION TO BRGY. SAN ROQUE TO BRGY. BANUYO FMR, BRGY. 02 POBLACION, SAN ROQUE AND BANUYO, MERCEDES, EASTERN SAMAR | On-Going | ₱5.0M |
| 24IB0094 | Jun 3, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN JOSE ELEMENTARY SCHOOL, BARANGAY SAN JOSE, MERCEDES, EASTERN SAMAR | Completed | ₱5.0M |
| 23IB0095 | Aug 3, 2023 | CONCRETING OF BRGY. SUNG-AN TO BRGY. BUSAY TO POBLACION 1 FMR, MERCEDES, EASTERN SAMAR | Completed | ₱19.9M |
| 23IB0116 | Aug 3, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, MERCEDES, EASTERN SAMAR | Completed | ₱9.8M |
| 23IB0057 | Mar 22, 2023 | CONSTRUCTION OF ROAD, BARANGAY CAMBANTE - BARANGAY BUSAY, MERCEDES, EASTERN SAMAR | Completed | ₱9.9M |
| 22IB0150 | Jan 16, 2023 | CONSTRUCTION OF 1STY2CL, BUSAY PRIMARY SCHOOL, MERCEDES, EASTERN SAMAR | Completed | ₱6.5M |
| 22IB0078 | Apr 7, 2022 | CONSTRUCTION OF BARANGAY ROAD AT BARANGAY SUNG-AN, BARANGAY CAGBUNGA AND BARANGAY BOBON, MERCEDES, EASTERN SAMAR | Completed | ₱4.9M |
| 21IB0005 | Oct 7, 2021 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUSAY ELEMENTARY SCHOOL, BARANGAY BUSAY, MERCEDES, EASTERN SAMAR | Completed | ₱3.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.