Project 22JC0068
DPWH infrastructure contract
Contract ID:
22JC0068
Fingerprint:
07f11626c7ac70…5806a160ce Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 26, 2022 (4 yrs 1 mo ago) · Target/actual end Nov 4, 2022
Description:
CONSTRUCTION OF 1 UNIT RAINWATER COLLECTION SYSTEM (RWCS) VERTICAL TANK WITH LAVATORY AT PANGANURAN NHS, BRGY. PANGANURAN, GUTALAC, ZAMBOANGA DEL NORTE
Category:
Water Provision and Storage
Implementing office:
DPWH Zamboanga del Norte 3rd DEO · Region IX
Contractor:
JGC CONSTRUCTION & ENTERPRISES · DPWH contractor code 34305
Contract amount:
₱316,256.76 (₱316.3K)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 47e1470f7b1d… | Sep 9, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA DEL NORT | ₱315,001.57 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JD0078 | Aug 21, 2025 | CONCRETING OF BRGY. LUX TO BRGY. SAS FMR, BRGY. LUX AND BRGY. SAS, GUTALAC, ZAMBOANGA DEL NORTE - MODIFIED TO: CONCRETING OF BRGY. LUX, GUTALAC, ZAMBOANGA DEL NORTE | On-Going | ₱14.5M |
| 23Z00033 | Apr 30, 2025 | CONTRACT PACKAGE 1C - CONSTRUCTION OF NEW TRANS-CENTRAL ROADS AND DRAINAGE | On-Going | ₱1.07B |
| 25J00011 | Mar 14, 2025 | CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER AT KIPIT BR. 2 SECTION (B01183MN) ALONG LILOY-SIOCON RD (S01146MN) (DOWNSTREAM - LEFT SI | On-Going | ₱145.6M |
| 25J00012 | Mar 14, 2025 | CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER AT KIPIT BR. 2 SECTION (B01183MN) ALONG LILOY-SIOCON RD (S01146MN) (UPSTREAM - LEFT SIDE | On-Going | ₱145.0M |
| 25JD0005 | Feb 17, 2025 | CONSTRUCTION OF ROAD, BARANGAY LUX, GUTALAC, ZAMBOANGA DEL NORTE | Completed | ₱14.7M |
| 25JD0023 | Feb 17, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY POBLACION, GUTALAC, ZAMBOANGA DEL NORTE | Completed | ₱11.8M |
| 25JD0028 | Feb 17, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL TRIBAL HALL), GUTALAC, ZAMBOANGA DEL NORTE | Completed | ₱4.9M |
| 25JD0036 | Feb 17, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2019 + 935 - K2019 + 945, ZAMBOANGA DEL NORTE | Completed | ₱1.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.