Project 22MH0053

DPWH infrastructure contract
Contract ID:
22MH0053
Fingerprint:
ac96c533a4f246…da7c2ef660 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2022 (4 yrs 8 mo ago) · Target/actual end May 15, 2023
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ROQUE, PALIMBANG, SULTAN KUDARAT
Category:
Buildings and Facilities
Implementing office:
Contractor:
BARRIST BUILDERS AND CONSTRUCTION SUPPLY · DPWH contractor code 39785
Contract amount:
₱4,950,000.00 (₱5.0M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
5a5bcfc6c209…Feb 21, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SULTAN KUDARAT 2ND₱4,825,371.90

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MH0124Aug 19, 2025CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMCompleted₱2.6M
25MH0022Mar 25, 2025CONSTRUCTION OF RIVER BANK PROTECTION (UPSTREAM LEFT SIDE), BARANGAY BARONGIS, PALIMBANG, SULTAN KUDARATCompleted₱120.6M
25MH0090Mar 21, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BALIANGO ELEMENTARY SCHOOL, BARANGAY BALIANGO, PALIMBANG, SULTAN KUDARATCompleted₱3.8M
25MH0092Mar 21, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY KOLONGKOLONG, PALIMBANG, SULTAN KUDARATCompleted₱2.9M
25MH0094Mar 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, PALIMBANG, SULTAN KUDARATCompleted₱4.8M
25MH0003Mar 19, 2025RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K1998+000 - K1999+197Completed₱21.0M
25MH0004Mar 19, 2025RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K2006+000 - K2006+892Completed₱15.7M
25MH0005Mar 17, 2025RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K2029+246 - K2030+000, K2044+087 - K2044+387Completed₱18.4M