Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23AD0067

DPWH infrastructure contract
Contract ID:
23AD0067
Fingerprint:
3a50f007252d7a…e3b8513b32 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 22, 2023 (3 yrs 7 mo ago) · Target/actual end Oct 11, 2024
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANAYOYO, ILOCOS SUR
Category:
Buildings and Facilities
Implementing office:
Contract amount:
₱9,506,073.72 (₱9.5M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AD0062May 23, 2025SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SALVADOR-LANGLANGCA, CITY OF CANDON, ILOCOS SURCompleted₱48.2M
25AD0010Feb 10, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANAYOYO, ILOCOS SURCompleted₱9.6M
24AD0077Apr 30, 2024CONSTRUCTION OF RIVER WALL AT DAGMAN ALONG TIKENG RIVER, POBLACION, QUIRINO, ILOCOS SURCompleted₱5.7M
24AD0036Mar 14, 2024CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF LANGLANGCA-SALVADOR FLOOD CONTROL STRUCTURE, CANDON CITY, ILOCOS SURCompleted₱49.0M
22AD0034May 19, 2022CONSTRUCTION/UPGRADING/REHABILTATION OF DRAINAGE ALONG NATIONAL ROAD-SECONDARY ROADS - CANDON BYPASS ROAD-K0349+250-K0349+510, CANDON CITY, ILOCOS SURCompleted₱4.8M
22AD0080Apr 4, 2022CONSTRUCTION OF BANAYOYO RIVER CONTROL, BANAYOYO, ILOCOS SURCompleted₱19.8M
21AD0105Feb 8, 2021CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), SITIO BAY-ASAN, BRGY. NAGUIMBA, BANAYOYO, ILOCOS SURCompleted₱5.8M
18AD0106May 23, 2018ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS-JCT.SANTIAGO-BANAYOYO-LIDLIDDA-SAN EMILIO-QUIRINO ROAD, K0353+609.40-K0354+000, K0354+000-K0354+962, K0354+962-K0355+294Completed₱8.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.