Project 24AD0036
DPWH infrastructure contract
Contract ID:
24AD0036
Fingerprint:
ee6a4ebed8eacd…dc50a72941 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 14, 2024 (2 yrs 7 mo ago) · Target/actual end Jun 25, 2024
Description:
CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF LANGLANGCA-SALVADOR FLOOD CONTROL STRUCTURE, CANDON CITY, ILOCOS SUR
Category:
Flood Control and Drainage
Implementing office:
DPWH Ilocos Sur 2nd DEO · Region I
Contractor:
NORTH TECH BUILDERS AND CONSTRUCTION SUPPLY · DPWH contractor code 37062
Contract amount:
₱48,989,188.24 (₱49.0M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 191bf9d2aace… | Mar 6, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOCOS SUR 2ND DEO | ₱47,516,243.54 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AD0062 | May 23, 2025 | SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SALVADOR-LANGLANGCA, CITY OF CANDON, ILOCOS SUR | Completed | ₱48.2M |
| 25AD0010 | Feb 10, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANAYOYO, ILOCOS SUR | Completed | ₱9.6M |
| 24AD0077 | Apr 30, 2024 | CONSTRUCTION OF RIVER WALL AT DAGMAN ALONG TIKENG RIVER, POBLACION, QUIRINO, ILOCOS SUR | Completed | ₱5.7M |
| 23AD0067 | Mar 22, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANAYOYO, ILOCOS SUR | Completed | ₱9.5M |
| 22AD0034 | May 19, 2022 | CONSTRUCTION/UPGRADING/REHABILTATION OF DRAINAGE ALONG NATIONAL ROAD-SECONDARY ROADS - CANDON BYPASS ROAD-K0349+250-K0349+510, CANDON CITY, ILOCOS SUR | Completed | ₱4.8M |
| 22AD0080 | Apr 4, 2022 | CONSTRUCTION OF BANAYOYO RIVER CONTROL, BANAYOYO, ILOCOS SUR | Completed | ₱19.8M |
| 21AD0105 | Feb 8, 2021 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), SITIO BAY-ASAN, BRGY. NAGUIMBA, BANAYOYO, ILOCOS SUR | Completed | ₱5.8M |
| 18AD0106 | May 23, 2018 | ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS-JCT.SANTIAGO-BANAYOYO-LIDLIDDA-SAN EMILIO-QUIRINO ROAD, K0353+609.40-K0354+000, K0354+000-K0354+962, K0354+962-K0355+294 | Completed | ₱8.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.