Project 23AH0002

DPWH infrastructure contract
Contract ID:
23AH0002
Fingerprint:
d459b967b328aa…d1bfd6a026 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2023 (3 yrs 8 mo ago) · Target/actual end Mar 30, 2023
Description:
ASSET PRESERVATION-PREVENTIVE MAINTENANCE ALONG PANG-LA UNION INTER-PROV'L RD, K0384+700-K0385+832,
Category:
Roads
Implementing office:
Contractor:
ARCINUE COMM'L. CORPORATION · DPWH contractor code 6746
As listed: ARCINUE COMM'L CORPORATION
Contract amount:
₱20,580,000.00 (₱20.6M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
a37d394aa37c…Jan 30, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 2ND₱20,105,179.56

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AH0126Jun 11, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. BUENLAG,MANGALDAN,PANGASINANOn-Going₱2.9M
25AH0130Jun 11, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. GUESANG,MANGALDAN,PANGASINANOn-Going₱1.9M
25AH0131Jun 11, 2025REHABILITATION OF ROAD, BARANGAY AMANSABINA,MANGALDAN, PANGASINANCompleted₱4.8M
25AH0173Mar 21, 2025CONCRETING OF BRGY. MALABAGO-BRGY.ALITAYA SERVICE ROAD FMR,BRGY. MALABAGO,MANGALDAN,PANGASINANCompleted₱14.4M
25AH0174Mar 21, 2025CONCRETING OF BRGY. SALAAN FMR,BRGY. SALAAN,MANGALDAN,PANGASINANCompleted₱14.5M
25AH0127Mar 20, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. POBLACION,MANGALDAN,PANGASINANCompleted₱1.9M
25A00286Feb 25, 2025WIDENING OF PERMANENT BRIDGES - EMBARCADERO BR. (B01329LZ) ALONG MANGALDAN-MANAOAG-BINALONAN RD (PHASE II)On-Going₱93.6M