Project 23BH0071
DPWH infrastructure contract
Contract ID:
23BH0071
Fingerprint:
1e82f4f91f3346…002d9a0e9f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2023 (3 yrs 8 mo ago) · Target/actual end Jun 19, 2023
Description:
BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION (COMPLETION) OF MULTI -PURPOSE BUILDING, BARANGAY AYOD,DINAPIGUE,ISABELA
Category:
Buildings and Facilities
Implementing office:
DPWH Isabela 4th DEO · Region II
Contractor:
JAY ARCIE CONSTRUCTION AND SUPPLY · DPWH contractor code 47153
Contract amount:
₱1,977,871.53 (₱2.0M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e1f065986edf… | Feb 7, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 4TH DEO | ₱1,920,500.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BH0120 | Aug 18, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DIBULO, DINAPIGUE, ISABELA | On-Going | ₱4.9M |
| 25BH0235 | Aug 18, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUCAL SUR, DINAPIGUE, ISABELA | On-Going | ₱4.8M |
| 25BH0300 | Aug 11, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY AYOD, DINAPIGUE, ISABELA | On-Going | ₱2.9M |
| 25BH0147 | Aug 6, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUCAL NORTE, DINAPIGUE, ISABELA | On-Going | ₱4.8M |
| 24BH0296 | Oct 7, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DIMALUADE FLOOD CONTROL STRUCTURE, SECTION 1, DINAPIGUE, ISABELA | Completed | ₱96.3M |
| 24BH0297 | Oct 4, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BUCAL NORTE FLOOD CONTROL STRUCTURE, SECTION 3, DINAPIGUE, ISABELA | On-Going | ₱96.3M |
| 24BH0298 | Sep 24, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BUCAL NORTE FLOOD CONTROL STRUCTURE, SECTION 4, DINAPIGUE, ISABELA | Completed | ₱96.5M |
| 24BH0299 | Sep 24, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DEDEKKEL FLOOD CONTROL STRUCTURE, SECTION 1, DINAPIGUE ISABELA | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.