Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23E00042

DPWH infrastructure contract
Contract ID:
23E00042
Fingerprint:
dad189cb122763…d3789c4f61 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 11, 2023 (3 yrs 9 mo ago) · Target/actual end Feb 5, 2024
Description:
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG MAG-ASAWANG TUBIG RIVER, SITIO 3 & 4, BRGY. SAN ANDRES SECTION, NAUJAN, OR. MINDO
Category:
GAA 2023 CSSP
Implementing office:
DPWH MIMAROPA Region · MIMAROPA Region
Contractor:
NEWBIG FOUR J CONSTRUCTION INC. · DPWH contractor code 15104
As listed: NEWBIG FOUR J CONSTRUCTION INC. (FORMERLY: FOUR J CONSTRUCTION)
Contract amount:
₱217,121,051.43 (₱217.1M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
d7c101c8ae39…Jan 31, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IV-B₱210,613,578.90

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26ED0013Aug 14, 2026RETROFITTING/STRENGTHENING OF MACATOC BR. (B00011MR) ALONG CALAPAN SOUTH RD, VICTORIA, ORIENTAL MINDOROOn-Going₱5.0M
25ED0217Jan 20, 2026REPAIR/REHABILITATION OF CLASSROOMS - AURORA CS, NAUJAN, ORIENTAL MINDOROOn-Going₱15.1M
25ED0212Jun 22, 2025REHABILITATION OF ROAD, BARANGAY MALINAO - BARANGAY STA. ISABEL, VICTORIA, ORIENTAL MINDOROOn-Going₱96.5M
25ED0181Jun 3, 2025CONSTRUCTION OF MULTI - PURPOSE BUILDING, NAUJAN, ORIENTAL MINDOROOn-Going₱4.9M
25E00235May 28, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. MISONG, STA. 000+000-STA. 000+345.83, NAUJAN, OR. MINDOROOn-Going₱230.9M
25ED0113May 21, 2025REHABILITATION OF NAUHAN BEACH ROAD, PAGKAKAISA - BAGONG BUHAY ROAD AND PINAHAN - BUHANGIN - NAG-IBA ROAD, NAUJAN, ORIENTAL MINDORO (PHASE 2)Completed₱96.0M
25ED0172May 21, 2025CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT), BARANGAY MAHABANG PARANG, NAUJAN, ORIENTAL MINDOROCompleted₱4.9M
25ED0176May 21, 2025CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY SAN CARLOS, NAUJAN, ORIENTAL MINDOROCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.