Project 23I00110
DPWH infrastructure contract
Contract ID:
23I00110
Fingerprint:
80431f9ae1cae5…7d890726a5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 5, 2023 (3 yrs 5 mo ago) · Target/actual end Jun 29, 2024
Description:
ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BAGAHUPI - BABATNGON - STA. CRUZ - BARUGO - CARIGARA RD. - (S00066LT) K097+(-310) - K0927+(-252), LEYTE 1ST LD
Category:
GAA 2023 OO-1
Implementing office:
DPWH Region VIII · Region VIII
Contractor:
AICON INDUSTRIES (48423) / CTC BUILDER AND SUPPLIES INCORPORATED (FOR. CTC BU · DPWH contractor code 12088
Contract amount:
₱96,297,408.38 (₱96.3M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IC0125 | Oct 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO, BABATNGON, LEYTE | Completed | ₱4.9M |
| 25I00150 | Jun 11, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM), RIZAL RIVER, BABATNGON, LEYTE | On-Going | ₱123.5M |
| 25I00163 | Jun 11, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM), RIZAL RIVER, BABATNGON, LEYTE | On-Going | ₱123.7M |
| 25IC0056 | Jun 5, 2025 | NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING -TERTIARY ROADS - BAGAHUPI-BABATNGON-STA CRUZ-BARUGO-CARIGARA ROAD - K0918 + 559 - K0918 + 992, K0922 + 000 - K0922 + 380, K0922 + 401 - K0923 + 000, BABATNGON, LEYTE | On-Going | ₱53.9M |
| 25IC0192 | Jun 5, 2025 | CONCRETING OF FMR AT BRGY. PINARIGUSAN TO LIPASAN FALLS, SAN MIGUEL, LEYTE | On-Going | ₱14.9M |
| 25IM0077 | May 28, 2025 | CONCRETING OF BRGY. STA. ELENA, TACLOBAN CITY TO BRGY. BAGONG SILANG, BABATNGON FMR, TACLOBAN CITY AND BABATNGON, LEYTE | On-Going | ₱49.7M |
| 25IC0053 | Apr 2, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - LEYTE-SAMAR INTER-PROVINCIAL ROAD - K0906 + 435 - K0906 + 676, BABATNGON, LEYTE | On-Going | ₱14.1M |
| 25IC0029 | Mar 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG RIZAL BRIDGE (DOWNSTREAM), BARANGAY RIZAL, BABATNGON, LEYTE | Completed | ₱96.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.