Project 23MD0045

DPWH infrastructure contract
Contract ID:
23MD0045
Fingerprint:
e2a34aa1035f6f…01decc437a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 22, 2023 (3 yrs 8 mo ago) · Target/actual end Dec 22, 2023
Description:
SITIO LIMATONG-CAMPO 1 AND KAGUIRINGAN FALLS LEADING TO HIKING JUMP-OFF SITE TO MT. AGKIR-AGKIR, NORTH COTABATO, PIGCAWAYAN, COTABATO
Category:
Bridges: Construction - Concrete (Superstructure) - without Piles, Bridges: Rehabilitation - Concrete (Superstructure) - without Piles, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Gravel, Roads: Construction - PCCP
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contract amount:
₱95,535,000.00 (₱95.5M)
Funding source:
Regular Infra - Bridges: Construction - Concrete (Superstructure) - without Piles, Bridges: Rehabilitation - Concrete (Superstructure) - without Piles, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Gravel, Roads: Construction - PCCP
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MD0044Jul 28, 2025CONSTRUCTION OF ROAD, SITIO PINAMULAAN - BARANGAY NORTH MANUANGAN - BARANGAY SOUTH MANUANGAN, PIGCAWAYAN, NORTH COTABATOCompleted₱4.9M
25MD0059Jul 7, 2025JCT. DAVAO - COTABATO (CROSSING BAGUER) - SITIO DALUMANGKOM - SITIO LAMPAKI ROAD, PIGKAWAYAN, NORTH COTABATOCompleted₱65.5M
25MD0012Mar 6, 2025CONSTRUCTION OF ROAD JCT. HIGHWAY - BULUAN ROAD, BARANGAY BULUAN, PIGCAWAYAN, NORTH COTABATOCompleted₱4.9M
25MD0030Mar 6, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY CAPAYURAN, PIGCAWAYAN, NORTH COTABATOCompleted₱4.9M
25MD0031Feb 27, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALOGO RIVER, UPSTREAM OF BALOGO BRIDGE, BARANGAY BALOGO, PIGCAWAYAN, COTABATOCompleted₱94.7M
25MD0038Feb 27, 2025CONSTRUCTION OF BALOGO RIVER FLOOD CONTROL STRUCTURE, ANICK SECTION, BARANGAY ANICK, PIGCAWAYAN, COTABATOCompleted₱94.4M
24MD0066May 15, 2024CONCRETING OF BRGY. MALU-AU TO BRGY. NEW CULASI FMR, BRGY. MALU-AU AND BRGY. NEW CULASI, PIGCAWAYAN, COTABATOCompleted₱9.9M
24MD0075May 15, 2024CONCRETING OF BRGY. BALOGO TO SITIO PAGLAUM FMR, BRGY. BALOGO, PIGCAWAYAN, COTABATOCompleted₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.