Project 23OB0383
DPWH infrastructure contract
Contract ID:
23OB0383
Fingerprint:
03d02b50e596d9…f8e7ce550f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 28, 2023 (2 yrs 10 mo ago) · Target/actual end Oct 22, 2024
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (RFU-NCR MEGA LABORATORY BUILDING) (WITH EQUIPMENT), 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
Location:
Not stated in the source
Contract amount:
₱81,188,147.02 (₱81.2M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 86aa1435f937… | Dec 19, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱81,188,147.02 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.