FY2026 GAA: ₱6.79T
PisoScan

Project 24C00002

DPWH infrastructure contract
Contract ID:
24C00002
Fingerprint:
8456774c84422f…7e7673fdb3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 6, 2024 (2 yrs 6 mo ago) · Target/actual end Dec 31, 2024
Description:
FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF AGUANG FLOOD CONTROL STRUCTURE, BALER AURORA (PHASE II), PROVINCE OF AURORA
Category:
GAA 2024 OO-2
Implementing office:
DPWH Region III · Region III
Contract amount:
₱146,679,617.40 (₱146.7M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CN0157Sep 1, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING , BARANGAY ZABALI, BALER, AURORAOn-Going₱99.0M
25CN0166Aug 27, 2025CONSTRUCTION OF ROAD (PHASE 2), BARANGAY ZABALI, BALER, AURORATerminated₱0
25CN0096Aug 4, 2025CONSTRUCTION OF ROAD, BARANGAY ZABALI, BALER, AURORACompleted₱28.9M
25CN0168Jul 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY CALABUANAN, BALER, AURORAOn-Going₱4.8M
25CN0116Jul 7, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY RESERVA, BALER, AURORAOn-Going₱6.9M
25CN0182Jul 3, 2025RAINWATER COLLECTOR SYSTEMOn-Going₱2.6M
25CN0150Jun 10, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG, BALER, AURORAOn-Going₱4.9M
25CN0021May 28, 2025REPLACEMENT OF PERMANENT WEAK BRIDGES, PUDOC BR. (B03014LZ) ALONG BALER - CASIGURAN RD (BALER - DINADIAWAN)On-Going₱65.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.