Project 24CN0117
DPWH infrastructure contract
Contract ID:
24CN0117
Fingerprint:
002679e73067a5…eaef50d829 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 15, 2024 (2 yrs 6 mo ago) · Target/actual end Dec 10, 2024
Description:
CONSTRUCTION OF ROAD, CALABUANAN, BALER, AURORA
Category:
Roads
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
CONRADO B. BAUTISTA CONST. & SUPPLY CORP. (FORMERL · DPWH contractor code 11411
Contract amount:
₱29,700,000.00 (₱29.7M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0157 | Sep 1, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING , BARANGAY ZABALI, BALER, AURORA | On-Going | ₱99.0M |
| 25CN0166 | Aug 27, 2025 | CONSTRUCTION OF ROAD (PHASE 2), BARANGAY ZABALI, BALER, AURORA | Terminated | ₱0 |
| 25CN0096 | Aug 4, 2025 | CONSTRUCTION OF ROAD, BARANGAY ZABALI, BALER, AURORA | Completed | ₱28.9M |
| 25CN0168 | Jul 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY CALABUANAN, BALER, AURORA | On-Going | ₱4.8M |
| 25CN0116 | Jul 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY RESERVA, BALER, AURORA | On-Going | ₱6.9M |
| 25CN0182 | Jul 3, 2025 | RAINWATER COLLECTOR SYSTEM | On-Going | ₱2.6M |
| 25CN0150 | Jun 10, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG, BALER, AURORA | On-Going | ₱4.9M |
| 25CN0021 | May 28, 2025 | REPLACEMENT OF PERMANENT WEAK BRIDGES, PUDOC BR. (B03014LZ) ALONG BALER - CASIGURAN RD (BALER - DINADIAWAN) | On-Going | ₱65.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.