Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24DD0231

DPWH infrastructure contract
Contract ID:
24DD0231
Fingerprint:
5229094a014f65…465ac6cf2c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 30, 2024 (2 yrs 3 mo ago) · Target/actual end Jan 6, 2025
Description:
CONCRETING OF BRGY. ESCRIBANO FMR, BRGY. ESCRIBANO, SAN JUAN, BATANGAS
Category:
Roads
Implementing office:
DPWH Batangas 4th DEO · Region IV-A
Contractor:
FALCON CROWNE KONSTRUCT CORP. · DPWH contractor code 56118
Contract amount:
₱14,477,523.00 (₱14.5M)
Funding source:
Outside Infra - GAA 2024 DA FMR
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25D00017May 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADSSAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 4, SAN JUAN BATANGASOn-Going₱89.4M
25D00018Apr 10, 2025CONSTRUCTION OF REVETMENT ALONG MALAKING ILOG RIVER, PHASE 1, BARANGAY MARAYKIT, SAN JUAN, BATANGASOn-Going₱94.1M
25D00027Apr 10, 2025WIDENING OF PERMANENT BRIDGES BANTILAN BR. (B02946LZ) ALONG SN JUAN-CANDELARIA JCT-CANDELARIA-BOLBOC RDOn-Going₱34.7M
25D00128Apr 10, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MALAKING TUBIG RIVER, PHASE 3, TIAONG, QUEZONOn-Going₱95.1M
25D00016Apr 4, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 3, SAN JUAN BATANGASOn-Going₱230.5M
25D00054Apr 4, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD), BATANGASOn-Going₱47.0M
24DD0300Mar 27, 2025CONCRETING OF BARANGAY PULANGBATO FMR, BARANGAY PULANGBATO, SAN JUAN, BATANGASOn-Going₱19.3M
24DD0303Mar 27, 2025CONCRETING OF BARANGAY SAMPIRO FMR, BARANGAY SAMPIRO, SAN JUAN, BATANGASOn-Going₱14.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.