Project 24EI0111
DPWH infrastructure contract
Contract ID:
24EI0111
Fingerprint:
74608f654a018a…552189b0e4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 9, 2024 (2 yrs 4 mo ago) · Target/actual end Apr 13, 2025
Description:
CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROAD - BONGABONG - SAGANA - ROXAS - SAN AQUILINO RD - K0112+022.00 - K0112+222.00, K0128+005.00 - K0128+396.00, BONGABONG - ROXAS, ORIENTAL MINDORO
Category:
GAA 2024 OO-1
Implementing office:
DPWH Southern Mindoro DEO · MIMAROPA Region
Contractor:
GREEN ISLAND ENTERPRISES · DPWH contractor code 36835
Contract amount:
₱16,947,475.89 (₱16.9M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e15fc0995b4d… | Jun 25, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTHERN MINDORO D | ₱17,054,351.95 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EI0063 | Jul 21, 2026 | ROAD WIDENING - SECONDARY ROADS - BONGABONG - SAGANA - ROXAS - SN AQUILINO RD - K0126+438 - K0126+539, K0126+635 - K0127+144, ROXAS, ORIENTAL MINDORO | On-Going | ₱17.4M |
| 26EI0101 | Jul 21, 2026 | CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CALAPAN SOUTH RD - K0138 + 928 - K0139 + 628, ROXAS, ORIENTAL MINDORO | On-Going | ₱16.6M |
| 26EI0058 | Jul 7, 2026 | ROAD WIDENING - SECONDARY ROADS - CALAPAN SOUTH RD - K0137 + 483 - K0137 + 786, K0140 + 405 - K0141 + 213, ROXAS, ORIENTAL MINDORO | On-Going | ₱49.4M |
| 26EI0127 | Jul 7, 2026 | ROAD WIDENING - SECONDARY ROADS - BONGABONG-SAGANA-ROXAS-SN AQUILINO RD-K0110+736 - K0111+334, K0115+078 - K0115+449, BONGABONG, ORIENTAL MINDORO | On-Going | ₱26.0M |
| 25EI0100 | Jun 16, 2025 | CONSTRUCTION OF ROAD AT DIMATULAC ST., SITIO MALIGAYA, BRGY. SAN AQUILINO, ROXAS, ORIENTAL MINDORO | Completed | ₱4.9M |
| 25EI0166 | Jun 16, 2025 | COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. ODIONG, ROXAS, ORIENTAL MINDORO, PHASE II | Completed | ₱2.9M |
| 25EI0046 | May 26, 2025 | IMPROVEMENT OF INTERSECTION AT CALAPAN SOUTH RD - K0140+000.00, BRGY. SAN AQUILINO, ROXAS, ORIENTAL MINDORO | Completed | ₱14.5M |
| 25EI0178 | May 26, 2025 | RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES: HAGAN BRIDGE, HAGAN, BONGABONG, ORIENTAL MINDORO | Completed | ₱24.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.