Project 24GA0153
DPWH infrastructure contract
Contract ID:
24GA0153
Fingerprint:
9358adfba0953b…dcfd038180 Verified
Status:
On-Going
Physical progress:
92.7%
Timeline:
Start Apr 23, 2024 (2 yrs 6 mo ago)
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, POBLACION, LEZO, AKLAN
Category:
Buildings and Facilities
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
E C GOLDEN CONSTRUCTION SERVICES CO. · DPWH contractor code 55346
Contract amount:
₱4,898,504.66 (₱4.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 64f4a1747f14… | Apr 16, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO | ₱4,898,504.66 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0115 | May 23, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BUGASONGAN, LEZO, AKLAN | On-Going | ₱2.0M |
| 25G00040 | Mar 6, 2025 | KALIBO CIRCUMFERENTIAL ROAD (MAKATO- LEZO SECTION), AKLAN | On-Going | ₱48.0M |
| 24GA0217 | Sep 10, 2024 | CONSTRUCTION OF 2STY8CL, LEZO IS, LEZO AKLAN | On-Going | ₱23.5M |
| 24GA0037 | May 28, 2024 | REHABILITATION OF ROAD, BARANGAY STA. CRUZ BIGA-A, LEZO, AKLAN | On-Going | ₱4.9M |
| 24G00003 | Feb 8, 2024 | KALIBO CIRCUMFERENTIAL ROAD (MAKATO- LEZO SECTION), AKLAN | On-Going | ₱193.0M |
| 24GA0044 | Feb 7, 2024 | CONSTRUCTION (COMPLETION) OF MPB BRGY. BAGTO, LEZO, AKLAN | Completed | ₱2.0M |
| 24GA0058 | Feb 7, 2024 | CONSTRUCTION (COMPLETION) OF MPB BRGY. IBAO, LEZO, AKLAN | Completed | ₱2.0M |
| 24GA0074 | Feb 6, 2024 | CONSTRUCTION (COMPLETION) OF MPB BRGY. STA. CRUZ, LEZO, AKLAN | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.