Project 25G00040
DPWH infrastructure contract
Contract ID:
25G00040
Fingerprint:
498b0159b7d6a8…ce507aac5c Verified
Status:
On-Going
Physical progress:
80.3%
Timeline:
Start Mar 6, 2025 (1 yr 8 mo ago)
Description:
KALIBO CIRCUMFERENTIAL ROAD (MAKATO- LEZO SECTION), AKLAN
Category:
GAA 2025 OO-1
Implementing office:
DPWH Region VI · Region VI
Contractor:
IBC INTERNATIONAL BUILDERS CORPORATION · DPWH contractor code 8576
Contract amount:
₱47,999,999.96 (₱48.0M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 1ac86a07304e… | Feb 24, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION VI | ₱47,999,999.96 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0115 | May 23, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BUGASONGAN, LEZO, AKLAN | On-Going | ₱2.0M |
| 24GA0217 | Sep 10, 2024 | CONSTRUCTION OF 2STY8CL, LEZO IS, LEZO AKLAN | On-Going | ₱23.5M |
| 24GA0037 | May 28, 2024 | REHABILITATION OF ROAD, BARANGAY STA. CRUZ BIGA-A, LEZO, AKLAN | On-Going | ₱4.9M |
| 24GA0153 | Apr 23, 2024 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, POBLACION, LEZO, AKLAN | On-Going | ₱4.9M |
| 24G00003 | Feb 8, 2024 | KALIBO CIRCUMFERENTIAL ROAD (MAKATO- LEZO SECTION), AKLAN | On-Going | ₱193.0M |
| 24GA0044 | Feb 7, 2024 | CONSTRUCTION (COMPLETION) OF MPB BRGY. BAGTO, LEZO, AKLAN | Completed | ₱2.0M |
| 24GA0058 | Feb 7, 2024 | CONSTRUCTION (COMPLETION) OF MPB BRGY. IBAO, LEZO, AKLAN | Completed | ₱2.0M |
| 24GA0074 | Feb 6, 2024 | CONSTRUCTION (COMPLETION) OF MPB BRGY. STA. CRUZ, LEZO, AKLAN | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.