Project 24GA0253
DPWH infrastructure contract
Contract ID:
24GA0253
Fingerprint:
e81c318782607f…9869c3d0b4 Verified
Status:
On-Going
Physical progress:
81.6%
Timeline:
Start Aug 20, 2025 (1 yr 2 mo ago)
Description:
REHABILITATION OF CONCRETING OF ALIPUTOS FMR, BRGY. ALIPUTOS, NUMANCIA, AKLAN
Category:
Trust Funds 2024
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
ABELARDE BUILDERS AND SUPPLY · DPWH contractor code 43170
Contract amount:
₱8,279,161.81 (₱8.3M)
Funding source:
Outside Infra - Trust Funds 2024
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0157 | Sep 18, 2025 | CONSTRUCTION OF SCHOOL BUILDING, KALIBO PILOT ELEMENTARY SCHOOL, BARANGAY POBLACION, KALIBO, AKLAN | On-Going | ₱14.9M |
| 25GA0023 | Jun 4, 2025 | CONSTRUCTION OF REVETMENT WALL ALONG AKLAN RIVER, BRGY. BACHAO SUR, KALIBO, AKLAN | On-Going | ₱60.8M |
| 25GA0122 | May 26, 2025 | CONSTRUCTION OF KALIBO GYMNASIUM, BARANGAY BAKHAW NORTE, KALIBO, AKLAN | On-Going | ₱98.5M |
| 25GA0121 | May 23, 2025 | CONSTRUCTION OF REVETMENT WALL IN BRGY. BAKHAW NORTE, KALIBO, AKLAN | On-Going | ₱9.6M |
| 25GA0040 | Apr 3, 2025 | CONSTRUCTION OF MABULAY ROAD, BARANGAY LINABUAN NORTE, KALIBO, AKLAN | Completed | ₱4.9M |
| 25GA0001 | Mar 21, 2025 | AKLAN EAST RD - K0281+000 - K0283+085 | On-Going | ₱93.6M |
| 24GA0251 | Mar 19, 2025 | CONSTRUCTION OF REVETMENT WALL (FLOOD CONTROL), ALONG AKLAN RIVER, KALIBO, AKLAN | On-Going | ₱24.1M |
| 25G00034 | Mar 6, 2025 | KALIBO CIRCUMFERENTIAL ROAD, KALIBO, AKLAN | On-Going | ₱52.8M |