Project 25GA0023

DPWH infrastructure contract
Contract ID:
25GA0023
Fingerprint:
9cd57ede9fa872…1b5fbbb166 Verified
Status:
On-Going
Physical progress:
55.0%
Timeline:
Start Jun 4, 2025 (1 yr 5 mo ago)
Description:
CONSTRUCTION OF REVETMENT WALL ALONG AKLAN RIVER, BRGY. BACHAO SUR, KALIBO, AKLAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
G.F. ROVERO MERCHANDISING · DPWH contractor code 27268
Contract amount:
₱60,762,222.20 (₱60.8M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
cdf06f6a6ba9…May 26, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO₱60,762,274.53

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0157Sep 18, 2025CONSTRUCTION OF SCHOOL BUILDING, KALIBO PILOT ELEMENTARY SCHOOL, BARANGAY POBLACION, KALIBO, AKLANOn-Going₱14.9M
24GA0253Aug 20, 2025REHABILITATION OF CONCRETING OF ALIPUTOS FMR, BRGY. ALIPUTOS, NUMANCIA, AKLANOn-Going₱8.3M
25GA0122May 26, 2025CONSTRUCTION OF KALIBO GYMNASIUM, BARANGAY BAKHAW NORTE, KALIBO, AKLANOn-Going₱98.5M
25GA0121May 23, 2025CONSTRUCTION OF REVETMENT WALL IN BRGY. BAKHAW NORTE, KALIBO, AKLANOn-Going₱9.6M
25GA0040Apr 3, 2025CONSTRUCTION OF MABULAY ROAD, BARANGAY LINABUAN NORTE, KALIBO, AKLANCompleted₱4.9M
25GA0001Mar 21, 2025AKLAN EAST RD - K0281+000 - K0283+085On-Going₱93.6M
24GA0251Mar 19, 2025CONSTRUCTION OF REVETMENT WALL (FLOOD CONTROL), ALONG AKLAN RIVER, KALIBO, AKLANOn-Going₱24.1M
25G00034Mar 6, 2025KALIBO CIRCUMFERENTIAL ROAD, KALIBO, AKLANOn-Going₱52.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.