FY2026 GAA: ₱6.79T
PisoScan

Project 24GB0067

DPWH infrastructure contract
Contract ID:
24GB0067
Fingerprint:
8f2e540dd8173d…e2289f1ff7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 9, 2024 (2 yrs 9 mo ago) · Target/actual end Jun 2, 2025
Description:
ODIONG-SIBALOM-SN REMIGIO-LEON RD-K0107 + 643 - K0107 + 805, K0129 + 245 - K0129 + 272 , K0130 + 195
Category:
Roads
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
Contract amount:
₱105,302,730.00 (₱105.3M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GB0087Jun 20, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIBALOM RIVER, SAN REMIGIO, ANTIQUE (PHASE 6)On-Going₱123.1M
24GB0157Jun 4, 2025REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG SIBALOM RIVER, BRGY. BAGUMBAYAN, SAN REMIGIO, ANTIQUE (RE-BID)Completed₱10.4M
25GB0070May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ODIONG - SIBALOM - SN REMIGIO - LEON RD - K0113+174 - K0117+000, ANTIQUEOn-Going₱113.8M
25GB0073May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BUGO - GEN FULLON RD - K0127+(-788) - K0127+036, K0129+503 - K0129+614, ANTIQUEOn-Going₱18.0M
24GB0158Mar 14, 2025REHABILITATION OF ODIONG-SIBALOM-SAN REMIGIO-LEON ROAD, K0120+460 - K0120+510, BRGY. CALAG-ITAN, SAN REMIGIO, ANTIQUEOn-Going₱10.1M
25G00065Mar 6, 2025SAN REMIGIO- BUGO- GEN FULLON- VALDERRAMA ROAD, ANTIQUEOn-Going₱149.1M
25GB0023Mar 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SINUNDULAN, SAN REMIGIO, ANTIQUECompleted₱4.9M
25GB0052Mar 4, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAN REMIGIO, ANTIQUEOn-Going₱7.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.