Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24M00007

DPWH infrastructure contract
Contract ID:
24M00007
Fingerprint:
9f52b7d3ba00af…b00fcee6a3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 9, 2024 (2 yrs 6 mo ago) · Target/actual end Apr 21, 2025
Description:
ROAD WIDENING - DIGOS-MAKAR RD - K1594 + 000 - K1597 + 800, K1600 + 167 - K1600+300, MALUNGON, SARANGANI
Category:
Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP
Implementing office:
DPWH Region XII · Region XII
Contractor:
JDRC CONSTRUCTION & SUPPLIES, CORP. · DPWH contractor code 33869
Contract amount:
₱164,029,020.38 (₱164.0M)
Funding source:
Regular Infra - Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
7d3f77aeb9aa…Apr 30, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII₱162,391,412.37

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25L00126Sep 12, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - MAHARLIKA HIGHWAY (DIGOS - MAKAR RD.) - K1589+861 - K1569+903, K1590+000 - K1590+224, DAVAO DEL SUROn-Going₱97.3M
25LD0173Jun 25, 2025CONSTRUCTION OF FLOOD MITIGATING STRUCTURE (CONCRETE REVETMENT/DIKE) ALONG MALALAG RIVER( STEEL BRIDGE, PUROK 2 & PUROK 3 SECTION), BRGY. IBO, MALALAG, DAVAO DEL SUROn-Going₱96.0M
25LD0146Jun 9, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE-CONCRETE REVETMENT ALONG PADADA-MAINIT RIVER (LAPULABAO-MASALAM BRIDGE DOWNSTREAM SECTION) HAGONOY, DAVAO DEL SURCompleted₱120.0M
25ME0009Mar 31, 2025NHW JCT. MALUNGON GAMAY - KIBAWALAN - PUROK ONSE LEADING TO BUSAGAN FALLS, MALUNGON, SARANGANI PROVINCECompleted₱9.5M
25LD0207Mar 26, 2025CONCRETING OF BRGY. BULACAN FMR, BRGY. BULACAN, MALALAG, DAVAO DEL SURCompleted₱14.4M
25LD0065Mar 24, 2025CONSTRUCTION OF FLOOD MITIGATING STRUCTURE ALONG MALALAG RIVER (IBO-PITO SECTION), BARANGAY IBO, MALALAG, DAVAO DEL SUROn-Going₱47.5M
25LD0071Mar 24, 2025PREVENTIVE MAINTENANCE OF ROAD; ASPHALT OVERLAY- DAVAO- SARANGANI COASTAL RD ( MALALAG- MALITA-JAS-G)- K1595+445-K1596+042, DAVAO DEL SUROn-Going₱24.9M
25LD0081Mar 24, 2025CONSTRUCTION (COMPLETION) OF MPB, BRGY. BOLTON, MALALAG, DAVAO DEL SURCompleted₱3.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.