Project 24M00319
DPWH infrastructure contract
Contract ID:
24M00319
Fingerprint:
99f97f320e464b…80c6380e4b Verified
Status:
On-Going
Physical progress:
96.2%
Timeline:
Start Aug 5, 2025 (1 yr 3 mo ago)
Description:
CONSTRUCTION OF ROAD, STA 0+000 - STA 1+200, BARANGAY SOLON, SULTAN MASTURA, MAGUINDANAO DEL NORTE
Category:
Unprogrammed Appropriations 2024
Implementing office:
DPWH Region XII · Region XII
Contractor:
MUST ENTERPRISES · DPWH contractor code 13336
Contract amount:
₱18,720,828.46 (₱18.7M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24M00331 | Jul 4, 2025 | IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF WATER SYSTEM LEVEL II AT CAMP PALAW PAYONG, MAKABISU, SULTAN MASTURA | On-Going | ₱9.9M |
| 25M00085 | Mar 14, 2025 | PREVENTIVE MAINTENANCE - SIMUAY LANDASAN-PARANG RD - K1866 + (-433) - K1867 + 135, SULTAN MASTURA, MAGUINDANAO DEL NORTE | Completed | ₱63.9M |
| 23M00182 | Oct 31, 2023 | CONSTRUCTION OF PARALLEL BRIDGE BESIDE TAPAYAN BRIDGE ALONG SIMUAY LANDASAN-PARANG RD (S01761MN) K1869+061 - K 1869+211 (BRIDGES) ; K186+223 - K 1869+373 (APPROACHES), SULTAN MASTURA, MAGUINDANAO | On-Going | ₱19.2M |
| 23M00186 | Oct 19, 2023 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND TRAINING CENTER, BRGY. KIRKIR, SULTAN MASTURA, MAGUINDANAO | Completed | ₱3.0M |
| 22M00110 | Dec 19, 2022 | REHABILITATION OF ROAD FROM SITIO PAYONG 2, BRGY. MACABISO TO SITIO MARGUES, STA. 0+000-STA. 0+521.5 BRGY. TAPAYAN, SULTAN MASTURA, MAGUINDANAO | Completed | ₱9.8M |
| 20MA0074 | Oct 22, 2020 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING), BRGY. TAPAYAN, SULTAN MASTURA, MAGUINDANAO | Completed | ₱3.0M |
| 20MA0012 | Feb 24, 2020 | CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. POBLACION, SULTAN MASTURA, MAGUINDANAO | Completed | ₱2.5M |
| 19MA0085 | Oct 17, 2019 | WIDENING OF COTABATO-LANAO ROAD, SULTAN MASTURA SECTION, SULTAN MASTURA, MAGUINDANAO | Completed | ₱96.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.