Physical progress:
54.4%
Timeline:
Start Apr 8, 2025 (1 yr 7 mo ago)
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONST./IMPR'VT. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-DINADIAWAN-DITAWINI BYPASS ROAD LEAD. TO TOURISM SITES/DESTINATIONS, BRGY. DITAWINI, DINALUNGAN, AU
Category:
Roads
Implementing office:
DPWH Region III · Region III
Contractor:
ZF CONSTRUCTION · DPWH contractor code 17676
Contract amount:
₱14,336,593.33 (₱14.3M)
Funding source:
Regular Infra - GAA 2025 CP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CN0089Jun 16, 2025CONSTRUCTION OF ROAD, BARANGAY PALEG, DINALUNGAN, AURORACompleted₱34.3M
25CN0023May 28, 2025RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, SALA BR. (B04212LZ) ALONG BALER-CASIGURAN RD (DINADIAWAN-CASIGURAN SECT)On-Going₱14.5M
25CN0122May 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION ZONE II, DINALUNGAN, AURORACompleted₱5.9M
25CN0147May 23, 2025CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY MAPALAD, DINALUNGAN, AURORACompleted₱5.0M
25CN0006Mar 26, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BALER - CASIGURAN RD (DINADIAWAN-CASIGURAN SECT) K0302+000 - K0302+520Completed₱18.1M
25CN0088Mar 24, 2025CONSTRUCTION OF ROAD, BARANGAY NIPOO, DINALUNGAN, AURORACompleted₱19.3M
25CN0090Mar 24, 2025CONSTRUCTION OF ROAD, BARANGAY POBLACION ZONE II, DINALUNGAN, AURORAOn-Going₱9.7M
25CN0103Mar 11, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY POBLACION ZONE II, DINALUNGAN, AURORACompleted₱48.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.