Project 25CN0006
DPWH infrastructure contract
Contract ID:
25CN0006
Fingerprint:
4321380716dbe9…67db0a2de7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 26, 2025 (1 yr 7 mo ago) · Target/actual end May 26, 2025
Description:
ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BALER - CASIGURAN RD (DINADIAWAN-CASIGURAN SECT) K0302+000 - K0302+520
Category:
Roads
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
ZF CONSTRUCTION · DPWH contractor code 17676
Contract amount:
₱18,127,369.88 (₱18.1M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2fc922be9854… | Mar 18, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO | ₱18,127,369.88 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0089 | Jun 16, 2025 | CONSTRUCTION OF ROAD, BARANGAY PALEG, DINALUNGAN, AURORA | Completed | ₱34.3M |
| 25CN0023 | May 28, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, SALA BR. (B04212LZ) ALONG BALER-CASIGURAN RD (DINADIAWAN-CASIGURAN SECT) | On-Going | ₱14.5M |
| 25CN0122 | May 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION ZONE II, DINALUNGAN, AURORA | Completed | ₱5.9M |
| 25CN0147 | May 23, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY MAPALAD, DINALUNGAN, AURORA | Completed | ₱5.0M |
| 25C00472 | Apr 8, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONST./IMPR'VT. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-DINADIAWAN-DITAWINI BYPASS ROAD LEAD. TO TOURISM SITES/DESTINATIONS, BRGY. DITAWINI, DINALUNGAN, AU | On-Going | ₱14.3M |
| 25CN0088 | Mar 24, 2025 | CONSTRUCTION OF ROAD, BARANGAY NIPOO, DINALUNGAN, AURORA | Completed | ₱19.3M |
| 25CN0090 | Mar 24, 2025 | CONSTRUCTION OF ROAD, BARANGAY POBLACION ZONE II, DINALUNGAN, AURORA | On-Going | ₱9.7M |
| 25CN0103 | Mar 11, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY POBLACION ZONE II, DINALUNGAN, AURORA | Completed | ₱48.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.