Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25D00025

DPWH infrastructure contract
Contract ID:
25D00025
Fingerprint:
fb00446bda7aa8…bcc9eae2d9 Verified
Status:
On-Going
Physical progress:
0%
Timeline:
Start Apr 10, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF BY-PASS AND DIVERSION ROADS STA. CRUZ - PAGSANJAN DIVERSION ROAD, LAGUNA
Category:
Roads
Implementing office:
DPWH Region IV-A · Region IV-A
Contract amount:
₱56,448,831.81 (₱56.4M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
14a81f30d1e0…Mar 24, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IV-A₱56,448,831.81

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DH0040Aug 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. CRUZ LAKESHORE, STA. CRUZ, LAGUNAOn-Going₱93.6M
25DH0066Jul 14, 2025REHABILITATION OF SEWERAGE SYSTEM, BARANGAY POBLACION 2, SANTA CRUZ, LAGUNAOn-Going₱9.6M
25DH0068Jun 30, 2025CONSTRUCTION/REHABILITATION OF RAINWATER COLLECTOR SYSTEM (6 UNITS)Completed₱2.6M
25DH0056Jun 25, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAGUNA STATE POLYTECHNIC UNIVERSITY, SANTA CRUZ CAMPUS, BARANGAY BUBUKAL, SANTA CRUZ, LAGUNACompleted₱19.2M
25DH0051May 26, 2025PREVENTIVE MAINTENANCE-PRIMARY ROADS CALAMBA-STA. CRUZ-FAMY JCT RD K0083+028-K0084+794, STA. CRUZ, LAGUNACompleted₱93.6M
25DH0035May 15, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY DUHAT, SANTA CRUZ, LAGUNAOn-Going₱19.1M
25DH0027Feb 18, 2025CONSTRUCTION OF RIVER CONTROL STRUCTURE ALONG SANTA CRUZ RIVER, SANTA CRUZ, LAGUNACompleted₱70.2M
25DH0008Feb 11, 2025ROAD WIDENING-PRIMARY ROADS-CALAMBA-STA. CRUZ-FAMY JCT RD-K0084+723-K0084+794, STA. CRUZ, LAGUNACompleted₱5.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.