Project 25DH0066
DPWH infrastructure contract
Contract ID:
25DH0066
Fingerprint:
98fbb991d28205…d331f0af43 Verified
Status:
On-Going
Physical progress:
89.1%
Timeline:
Start Jul 14, 2025 (1 yr 3 mo ago)
Description:
REHABILITATION OF SEWERAGE SYSTEM, BARANGAY POBLACION 2, SANTA CRUZ, LAGUNA
Category:
GAA 2025 SSP
Implementing office:
DPWH Laguna 1st DEO · Region IV-A
Contractor:
JA.VI CONSTRUCTION · DPWH contractor code 52920
Contract amount:
₱9,594,461.12 (₱9.6M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DH0040 | Aug 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. CRUZ LAKESHORE, STA. CRUZ, LAGUNA | On-Going | ₱93.6M |
| 25DH0068 | Jun 30, 2025 | CONSTRUCTION/REHABILITATION OF RAINWATER COLLECTOR SYSTEM (6 UNITS) | Completed | ₱2.6M |
| 25DH0056 | Jun 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAGUNA STATE POLYTECHNIC UNIVERSITY, SANTA CRUZ CAMPUS, BARANGAY BUBUKAL, SANTA CRUZ, LAGUNA | Completed | ₱19.2M |
| 25DH0051 | May 26, 2025 | PREVENTIVE MAINTENANCE-PRIMARY ROADS CALAMBA-STA. CRUZ-FAMY JCT RD K0083+028-K0084+794, STA. CRUZ, LAGUNA | Completed | ₱93.6M |
| 25DH0035 | May 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY DUHAT, SANTA CRUZ, LAGUNA | On-Going | ₱19.1M |
| 25D00025 | Apr 10, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS STA. CRUZ - PAGSANJAN DIVERSION ROAD, LAGUNA | On-Going | ₱56.4M |
| 25DH0027 | Feb 18, 2025 | CONSTRUCTION OF RIVER CONTROL STRUCTURE ALONG SANTA CRUZ RIVER, SANTA CRUZ, LAGUNA | Completed | ₱70.2M |
| 25DH0008 | Feb 11, 2025 | ROAD WIDENING-PRIMARY ROADS-CALAMBA-STA. CRUZ-FAMY JCT RD-K0084+723-K0084+794, STA. CRUZ, LAGUNA | Completed | ₱5.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.