Project 25GD0009
DPWH infrastructure contract
Contract ID:
25GD0009
Fingerprint:
c71ba64545445a…44959645b5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2025 (1 yr 7 mo ago) · Target/actual end May 2, 2025
Description:
CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CABANGAHAN, PANITAN, CAPIZ
Category:
GAA 2025 SSP
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
VINLIX CONSTRUCTION · DPWH contractor code 55653
Contract amount:
₱4,949,356.37 (₱4.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 857948c5709c… | Mar 5, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO | ₱4,897,361.85 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GD0042 | Jun 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MAAYON, CAPIZ | On-Going | ₱9.9M |
| 25GD0047 | Jun 9, 2025 | MAAYON BY-PASS ROAD, CAPIZ | On-Going | ₱4.9M |
| 25G00068 | Mar 24, 2025 | CONSTRUCTION OF MULTI- PURPOSE BUILDING (EVACUATION FACILITIES), BARANGAY INDAYAGAN, MAAYON CAPIZ | On-Going | ₱48.2M |
| 25GD0015 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY FERNANDEZ, MAAYON, CAPIZ | On-Going | ₱4.9M |
| 25GH0091 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LAYOGBATO, LEMERY, ILOILO | Completed | ₱2.9M |
| 25GD0018 | Mar 17, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY JEBACA, MAAYON, CAPIZ | On-Going | ₱4.9M |
| 25G00053 | Mar 6, 2025 | MAAYON- SARA BYPASS ROAD, CAPIZ | On-Going | ₱36.5M |
| 24GD0066 | Oct 31, 2024 | CONCRETING OF BRGY. OLD GUIA FMR PHASE II, BRGY. OLD GUIA, MAAYON, CAPIZ | On-Going | ₱12.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.