Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25GD0018

DPWH infrastructure contract
Contract ID:
25GD0018
Fingerprint:
e60093272d4f5b…6edc7371ed Verified
Status:
On-Going
Physical progress:
99.2%
Timeline:
Start Mar 17, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY JEBACA, MAAYON, CAPIZ
Category:
GAA 2025 SSP
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
BROOKLYN & CONNOR BUILDERS · DPWH contractor code 43710
Contract amount:
₱4,920,000.00 (₱4.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
527fd03a742d…Feb 27, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO₱4,920,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GD0042Jun 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MAAYON, CAPIZOn-Going₱9.9M
25GD0047Jun 9, 2025MAAYON BY-PASS ROAD, CAPIZOn-Going₱4.9M
25G00068Mar 24, 2025CONSTRUCTION OF MULTI- PURPOSE BUILDING (EVACUATION FACILITIES), BARANGAY INDAYAGAN, MAAYON CAPIZOn-Going₱48.2M
25GD0009Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CABANGAHAN, PANITAN, CAPIZCompleted₱4.9M
25GD0015Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY FERNANDEZ, MAAYON, CAPIZOn-Going₱4.9M
25GH0091Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LAYOGBATO, LEMERY, ILOILOCompleted₱2.9M
25G00053Mar 6, 2025MAAYON- SARA BYPASS ROAD, CAPIZOn-Going₱36.5M
24GD0066Oct 31, 2024CONCRETING OF BRGY. OLD GUIA FMR PHASE II, BRGY. OLD GUIA, MAAYON, CAPIZOn-Going₱12.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.