Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25IF0019

DPWH infrastructure contract
Contract ID:
25IF0019
Fingerprint:
9aabf1c184b53f…ba245a4d1a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 4, 2025 (1 yr 8 mo ago) · Target/actual end Aug 20, 2025
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CANDELARIA, MATAG-OB, LEYTE
Category:
GAA 2025 SSP
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contractor:
RJIR ENTERPRISES CORPORATION · DPWH contractor code 34843
Contract amount:
₱9,849,999.29 (₱9.8M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IF0114May 4, 2026LAST MILE SCHOOLS PROGRAM - MASABA I ELEMENTARY SCHOOL, PALOMPON, LEYTEOn-Going₱12.6M
25IF0088Jun 19, 2025CONCRETING OF BRGY. MALAZARTE - BRGY. CAMBADBAD FMR, BRGY. MALAZARTE AND BRGY. CAMBADBAD, MATAG-OB, LEYTEOn-Going₱49.7M
25IF0065Mar 26, 2025CONSTRUCTION OF ROAD, SITIO CAMANSI, BARANGAY STA. ROSA, MATAG-OB, LEYTEOn-Going₱24.0M
25IF0006Feb 21, 2025CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE, BARANGAY RIVERSIDE, MATAG-OB, LEYTEOn-Going₱48.2M
25IF0028Feb 21, 2025CONSTRUCTION (COMPLETION) OF ROAD - BARANGAY MANLILINAO - BARANGAY SAN SEBASTIAN, ORMOC CITYCompleted₱48.9M
25IF0035Feb 20, 2025CONSTRUCTION OF CONCRETE ROAD, BARANGAY CACAO, KANANGA, LEYTECompleted₱5.9M
24I00268Jan 13, 2025CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - MATAG-OB SUPER HEALTH CENTER, LEYTE, MATAG-OB, LEYTEOn-Going₱11.9M
24IF0091Aug 5, 2024CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), SAN IGNACIO BARANGAY HALL, BARANGAY SAN IGNACIO, KANANGA, LEYTE; KANANGA NATIONAL HIGH SCHOOL, BARANGAY POBLACION, KANANGA, LEYTE; KANANGA NATIONAL HIGH SCHOOL - KAWAYAN ANNEX, BARANGAY KAWAYAN, KANANGA,Completed₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.