Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25IF0114

DPWH infrastructure contract
Contract ID:
25IF0114
Fingerprint:
296ddbfb7b1703…c13515da9d Verified
Status:
On-Going
Physical progress:
11.4%
Timeline:
Start May 4, 2026 (6 mos ago)
Description:
LAST MILE SCHOOLS PROGRAM - MASABA I ELEMENTARY SCHOOL, PALOMPON, LEYTE
Category:
GAA 2025 DepEd Last Mile Schools Program
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contractor:
HAMMERTEC CONSTRUCTION · DPWH contractor code 55774
Contract amount:
₱12,585,329.85 (₱12.6M)
Funding source:
Outside Infra - GAA 2025 DepEd Last Mile Schools Program
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IF0088Jun 19, 2025CONCRETING OF BRGY. MALAZARTE - BRGY. CAMBADBAD FMR, BRGY. MALAZARTE AND BRGY. CAMBADBAD, MATAG-OB, LEYTEOn-Going₱49.7M
25IF0065Mar 26, 2025CONSTRUCTION OF ROAD, SITIO CAMANSI, BARANGAY STA. ROSA, MATAG-OB, LEYTEOn-Going₱24.0M
25IF0019Mar 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CANDELARIA, MATAG-OB, LEYTECompleted₱9.8M
25IF0006Feb 21, 2025CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE, BARANGAY RIVERSIDE, MATAG-OB, LEYTEOn-Going₱48.2M
25IF0028Feb 21, 2025CONSTRUCTION (COMPLETION) OF ROAD - BARANGAY MANLILINAO - BARANGAY SAN SEBASTIAN, ORMOC CITYCompleted₱48.9M
25IF0035Feb 20, 2025CONSTRUCTION OF CONCRETE ROAD, BARANGAY CACAO, KANANGA, LEYTECompleted₱5.9M
24I00268Jan 13, 2025CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - MATAG-OB SUPER HEALTH CENTER, LEYTE, MATAG-OB, LEYTEOn-Going₱11.9M
24IF0091Aug 5, 2024CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), SAN IGNACIO BARANGAY HALL, BARANGAY SAN IGNACIO, KANANGA, LEYTE; KANANGA NATIONAL HIGH SCHOOL, BARANGAY POBLACION, KANANGA, LEYTE; KANANGA NATIONAL HIGH SCHOOL - KAWAYAN ANNEX, BARANGAY KAWAYAN, KANANGA,Completed₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.