Project 25IF0024
DPWH infrastructure contract
Contract ID:
25IF0024
Fingerprint:
1201bf976ceb3a…b56d3a8e99 Verified
Status:
On-Going
Physical progress:
98.4%
Timeline:
Start Feb 25, 2025 (1 yr 8 mo ago)
Description:
CONSTRUCTION OF TUGBONG FLOOD CONTROL (DOWNSTREAM) BARANGAY TUGBONG, KANANGA, LEYTE
Category:
GAA 2025 OO-2
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contractor:
LEDA CONSTRUCTION INCORPORATED · DPWH contractor code 12229
Contract amount:
₱96,379,043.24 (₱96.4M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 470c14e0a4c6… | Feb 14, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 4TH DEO | ₱96,379,043.24 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IF0098 | Sep 2, 2025 | CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, KANANGA, LEYTE | Completed | ₱29.7M |
| 25IF0048 | Jul 1, 2025 | ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - LIBUNGAO - MATAG-OB - PALOMPON RD - K0991+460 - K0992+000 | Completed | ₱43.0M |
| 25IF0016 | Mar 26, 2025 | CONSTRUCTION OF CANAWAGAN FLOOD CONTROL (UPSTREAM) POBLACION AND BRGY. NATUBGAN, KANANGA, LEYTE | On-Going | ₱96.4M |
| 25IF0012 | Mar 25, 2025 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - LIBUNGAO - MATAG-OB - PALOMPON RD - K0995+580 - K0996+128.1, K0996+172 - K0996+673.5, K0996+700 - K0996+980, K0998+518 - K0998+993 | On-Going | ₱33.4M |
| 25IF0071 | Mar 20, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - BAO BRIDGE (B00184LT) ALONG PALO-CARIGARA-ORMOC ROAD | Completed | ₱14.5M |
| 25IF0061 | Mar 18, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD - K0984+(-361.4)-K0984+(-264), K0984+088 - K0984+238, K0985+063 - K0985+160, K0985+774 - K0985+800, K0989+645 - K0989+705, K0990+ | On-Going | ₱19.5M |
| 25IF0054 | Mar 3, 2025 | ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD - K0988+065 - K0989+068 | Completed | ₱66.3M |
| 25IF0009 | Feb 26, 2025 | CONSTRUCTION OF SANTO NIÑO FLOOD CONTROL STRUCTURE, BARANGAY SANTO NIÑO, KANANGA, LEYTE | On-Going | ₱96.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.