Project 25N00150
DPWH infrastructure contract
Contract ID:
25N00150
Fingerprint:
b1a3db71de0e55…18b739603b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 21, 2025 (1 yr 8 mo ago) · Target/actual end Aug 19, 2025
Description:
CARAC-AN PARALLEL BR. ALONG SURIGAO-DAVAO COASTAL RD
Category:
Bridges
Implementing office:
DPWH Region XIII · Region XIII
Contractor:
J. M. LUCIANO CONSTRUCTION, INC. · DPWH contractor code 2083
As listed: J.M. LUCIANO CONSTRUCTION, INC.
Contract amount:
₱46,819,246.98 (₱46.8M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2ce6e7d6ee06… | Feb 14, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XIII (CARAG | ₱46,819,251.75 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25NH0082 | Jul 25, 2025 | REHABILITATION OF ROAD, BRGY. SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱29.0M |
| 25N00251 | Jul 18, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY SAN ANTONIO, MADRID, SURIGAO DEL SUR | On-Going | ₱238.1M |
| 25NH0087 | May 30, 2025 | CONSTRUCTION OF ROAD, BRGY. SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱4.8M |
| 25NH0065 | Apr 11, 2025 | CONSTRUCTION OF ROAD, BARANGAY SONGKIT, MADRID, SURIGAO DEL SUR | Completed | ₱19.5M |
| 25NH0032 | Feb 24, 2025 | CONSTRUCTION OF ROAD, BARANGAY LINIBUNAN, MADRID, SURIGAO DEL SUR | Completed | ₱13.8M |
| 24NH0125 | Jan 15, 2025 | CONST. OF ROADS AT BARANGAY SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱48.2M |
| 24NH0081 | Jun 3, 2024 | CONCRETING OF PUROK 2, BRGY. ESPERANZA TO SITIO BOYAKAN, BRGY. SAN VICENTE FMR, BRGY. ESPERANZA & BRGY. SAN VICENTE, CARMEN & MADRID, SURIGAO DEL SUR | Completed | ₱29.8M |
| 24N00149 | May 17, 2024 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SAN ANTONIO, MADRID, SURIGAO DEL SUR | Completed | ₱193.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.