Project 25N00251
DPWH infrastructure contract
Contract ID:
25N00251
Fingerprint:
9f62b696c1fee1…58102b55e0 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Jul 18, 2025 (1 yr 3 mo ago)
Description:
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY SAN ANTONIO, MADRID, SURIGAO DEL SUR
Category:
GAA 2025 SSP
Implementing office:
DPWH Region XIII · Region XIII
Contractor:
EQUI-PARCO CONSTRUCTION COMPANY · DPWH contractor code 14332
Contract amount:
₱238,109,912.64 (₱238.1M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25NH0082 | Jul 25, 2025 | REHABILITATION OF ROAD, BRGY. SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱29.0M |
| 25NH0087 | May 30, 2025 | CONSTRUCTION OF ROAD, BRGY. SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱4.8M |
| 25NH0065 | Apr 11, 2025 | CONSTRUCTION OF ROAD, BARANGAY SONGKIT, MADRID, SURIGAO DEL SUR | Completed | ₱19.5M |
| 25NH0032 | Feb 24, 2025 | CONSTRUCTION OF ROAD, BARANGAY LINIBUNAN, MADRID, SURIGAO DEL SUR | Completed | ₱13.8M |
| 25N00150 | Feb 21, 2025 | CARAC-AN PARALLEL BR. ALONG SURIGAO-DAVAO COASTAL RD | Completed | ₱46.8M |
| 24NH0125 | Jan 15, 2025 | CONST. OF ROADS AT BARANGAY SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱48.2M |
| 24NH0081 | Jun 3, 2024 | CONCRETING OF PUROK 2, BRGY. ESPERANZA TO SITIO BOYAKAN, BRGY. SAN VICENTE FMR, BRGY. ESPERANZA & BRGY. SAN VICENTE, CARMEN & MADRID, SURIGAO DEL SUR | Completed | ₱29.8M |
| 24N00149 | May 17, 2024 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SAN ANTONIO, MADRID, SURIGAO DEL SUR | Completed | ₱193.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.