Project 24C00551
DPWH infrastructure contract
Contract ID:
24C00551
Fingerprint:
652ca52155ac2e…0a0e623b74 Verified
Status:
On-Going
Physical progress:
1.6%
Timeline:
Start Aug 8, 2024 (2 yrs 3 mo ago)
Description:
CONVERGENCE & SPL. SUPP. PROG.-CONST./IMPR'VT. OF ACCESS RDS. LEAD. TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRA. PROG.-TRIP), DINADIAWAN-DITAWINI BYPASS ROAD LEAD. TO TOURISM SITES/DESTINATIONS, BRGY. DITAWINI, DINALUNGAN, PROV. OF AURORA
Category:
Roads
Implementing office:
DPWH Region III · Region III
Contractor:
ZF CONSTRUCTION · DPWH contractor code 17676
Contract amount:
₱96,968,133.77 (₱97.0M)
Funding source:
Regular Infra - GAA 2024 CP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 12829bd9f300… | Jul 22, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION III | ₱96,968,133.77 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0089 | Jun 16, 2025 | CONSTRUCTION OF ROAD, BARANGAY PALEG, DINALUNGAN, AURORA | Completed | ₱34.3M |
| 25CN0023 | May 28, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, SALA BR. (B04212LZ) ALONG BALER-CASIGURAN RD (DINADIAWAN-CASIGURAN SECT) | On-Going | ₱14.5M |
| 25CN0122 | May 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION ZONE II, DINALUNGAN, AURORA | Completed | ₱5.9M |
| 25CN0147 | May 23, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY MAPALAD, DINALUNGAN, AURORA | Completed | ₱5.0M |
| 25C00472 | Apr 8, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONST./IMPR'VT. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-DINADIAWAN-DITAWINI BYPASS ROAD LEAD. TO TOURISM SITES/DESTINATIONS, BRGY. DITAWINI, DINALUNGAN, AU | On-Going | ₱14.3M |
| 25CN0006 | Mar 26, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BALER - CASIGURAN RD (DINADIAWAN-CASIGURAN SECT) K0302+000 - K0302+520 | Completed | ₱18.1M |
| 25CN0088 | Mar 24, 2025 | CONSTRUCTION OF ROAD, BARANGAY NIPOO, DINALUNGAN, AURORA | Completed | ₱19.3M |
| 25CN0090 | Mar 24, 2025 | CONSTRUCTION OF ROAD, BARANGAY POBLACION ZONE II, DINALUNGAN, AURORA | On-Going | ₱9.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.