FY2026 GAA: ₱6.79T
PisoScan

Project 24GA0111

DPWH infrastructure contract
Contract ID:
24GA0111
Fingerprint:
b1b09dfd932a94…84c2edceac Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 25, 2024 (2 yrs 7 mo ago) · Target/actual end Aug 12, 2024
Description:
REHABILITATION OF MPB BRGY. ESTANCIA, KALIBO, AKLAN
Category:
Buildings and Facilities
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
INAMARGA ENTERPRISES · DPWH contractor code 26728
Contract amount:
₱4,825,000.00 (₱4.8M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1379cee09323…Mar 13, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO₱4,775,878.74

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0157Sep 18, 2025CONSTRUCTION OF SCHOOL BUILDING, KALIBO PILOT ELEMENTARY SCHOOL, BARANGAY POBLACION, KALIBO, AKLANOn-Going₱14.9M
24GA0253Aug 20, 2025REHABILITATION OF CONCRETING OF ALIPUTOS FMR, BRGY. ALIPUTOS, NUMANCIA, AKLANOn-Going₱8.3M
25GA0023Jun 4, 2025CONSTRUCTION OF REVETMENT WALL ALONG AKLAN RIVER, BRGY. BACHAO SUR, KALIBO, AKLANOn-Going₱60.8M
25GA0122May 26, 2025CONSTRUCTION OF KALIBO GYMNASIUM, BARANGAY BAKHAW NORTE, KALIBO, AKLANOn-Going₱98.5M
25GA0121May 23, 2025CONSTRUCTION OF REVETMENT WALL IN BRGY. BAKHAW NORTE, KALIBO, AKLANOn-Going₱9.6M
25GA0040Apr 3, 2025CONSTRUCTION OF MABULAY ROAD, BARANGAY LINABUAN NORTE, KALIBO, AKLANCompleted₱4.9M
25GA0001Mar 21, 2025AKLAN EAST RD - K0281+000 - K0283+085On-Going₱93.6M
24GA0251Mar 19, 2025CONSTRUCTION OF REVETMENT WALL (FLOOD CONTROL), ALONG AKLAN RIVER, KALIBO, AKLANOn-Going₱24.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.